House Update 3/20/09

by admin on March 23, 2009

Gentlemen –

Here is an update on the progress of the new chpater house as of 03/20/2009.

The foundation and basememnt footing have been poured.   A total of 107 cubic yards of concrete has been poured and 28,000 pounds of rebar installed.  These amounts reflect the sizing needed for a future third level to be added to the house.

Concrete retaining walls will be poured this week.  First level precast plank drawings are at the engineers for review.  Planks are 1 month out from approved shop drawings.  We will be working on basement structural steel and CMU walls, electrical and plumbing slab rough over the next 4 weeks.

Below are some photos of the foundation/basement pourings.  Enjoy and look for many more photos of the house progress to be posted.